Mould Project General Situation of Long Line Segment Casting for Spain Client
Product Name: Mould
Casting Method:
Long Line Segment Casting
Whole Bridge Segment: 476 Pieces
Project Location: Spain
In the whole project, the straight span and pier segment adopt casting-in-situ method, the rest spans all use precast
balancing cantilever method. Girder height at the box girder pedestal place is 7.0m (casting-in-situ), other precast girders and casting-in-situ girders weight are 6.0m. For segment casting method
Whole bridge length includes segment box girder 476 pieces. 4 m segments girders includes 368 pieces. 3.5m segment girders includes 56 pieces. 3m segment girders includes 4 pieces. 2m segment girders includes 48m. 0.5m wet joint seam includes 56 point.
In the project with long line segment casting method, the construction of continuous box girder with precast balancing cantilever method shall ensure that the joint between the girder and the girder joints is tight after installation.The integral linear shape of the continuous beam (including the linear and vertical lines) shall be guaranteed.
The mould project of long line segment casting, our overseas engineers have completed the inspection of electrical circuits and the commissioning of hydraulic devices, and the mould began to operate smoothly.